Construction Update

Construction Update- June 26
Posted on 06/26/2020

Previous week ending June 26, 2020:


▪ Footing and foundation excavation NE corner foundations, Stoops removed from old electrical room
▪ Steel Erection PAC moving North to grid 5.5
▪ Weight Room to be complete 6/27, Equipment Arrives 6/29
▪ Elevator Shaft complete by 6/29, CMU west wall PAC will start.
▪ Area A additional windows cut in for old Library, new rooms D220, D217
▪ Area A inspection next week, all classrooms second floor , 5 rooms 1st floor to be ready for finishes
▪ New addition classrooms (6) finished, need to close chase for Unit heaters
▪ All NW area foundation found to be good, final concrete poured NW corner PAC
▪ Window replacement complete except for hallway A & C windows
▪ Area C demo complete except minor door and wall openings.

Planned for the week ending July 3, 2020:

▪ New Foundations poured NE corner PAC, Current Footings inspected for compliance
▪ Steel erection to grid 4.9, half way mark, beginning of Auditorium
▪ Wood Shop area Wall Demo Complete
▪ Storm Water utility lines scoped and corrected, South Parking demo continues
▪ South Entrance framing stats for entrance, Media Center
▪ Area C framing for rooms completed, Bathroom Demo 1st, 2nd floor completed
▪ Area D Bathrooms completed and inspected along with weight Room