Construction Update

Construction Update- November 13, 2020
Posted on 11/13/2020

Previous week ending November 13, 2020:

▪ Started Underground Storm Drain installation
▪ Area A and C Lockers installation ongoing
▪ Underground plumbing getting installed
▪ Excavation for North Stage wall footing and foundation.
▪ Roof leader piping installed
▪ Electrical underground
▪ Bar joist installation in Theater almost completed
▪ Roof Decking for Theater almost completed

Planned for the week ending November 20, 2020:

▪ Roofing over Kitchen expected to start
▪ Curtain wall in fabrication, expecting delivery and install
▪ Electrical and Plumbing installation on going
▪ Storm drain install in PAC progressing
▪ Locker installation completion this week
▪ Install Glass in curtain wall
▪ Setting up for Temp Heat
▪ Set Roof Decking on NW Corner of PAC expected to start


Click here to view the full weekly progress report with pictures
Website by SchoolMessenger Presence. © 2020 Intrado Corporation. All rights reserved.