Construction Update

Construction Update- February 26, 2021
Posted on 02/26/2021

Week ending February 26, 2021

▪ Painting ceiling in the PAC
▪ HVAC / Plumbing complete in PAC Ceiling
▪ Forming for radius seating in PAC
▪ Drywall in Commons
▪ Tape in commons
▪ Tile in commons bathrooms
▪ Elevator certification and checkout
▪ Painting in commons
▪ Glazing and store fronts in Media Center
▪ Ceiling grid in Media Center
▪ Painting in classroom
▪ Cabinets and casework in Media center
▪ Kitchen concrete
▪ Lighting in Media and Commons
▪ Painting PAC Storage Room

Upcoming Week ending March 5, 2021
▪ Pouring shop floor
▪ Pouring PAC seating floor
▪ Continue painting ceiling in PAC
▪ Bathroom tile
▪ Drywall and Paint in commons
▪ Kitchen framing and rough ins

Click here to view updated pictures