Construction Update

Construction Update- March 26, 2021
Posted on 03/19/2021

Week ending March 26, 2021

▪ Terrazzo completed in south area of commons including wax
▪ Ceiling grid and lighting complete in commons
▪ Fire protections completed on 2nd floor and continuing first floor.
▪ Constructing clouds for the PAC on the ground and hanging from ceiling
▪ Pouring floor on each side of the stage
▪ Completed upper lower seating concrete
▪ Ceiling painting completed in PAC
▪ Kitchen plumbing inspections complete

Upcoming Week ending April 2, 2021
▪ Pouring PAC seating lower
▪ PAC electrical and Plumbing
▪ Terrazzo continues in commons working in the NW hallway
▪ Kitchen drywall and equipment

Click here to view updated pictures